Project Plan
Work will be completed in three phases
commencing on October 7, 2008, with pick-up of car with an
initial goal of completion by May 24, 2009. Our goal it to
complete all of the efforts ourselves, although some work may be
outsourced if our goal dates approach too quickly.
Additional goal has been added to complete
prior to VTR Regional competition in Austin, Texas, in April
2009.
Teardown - removal of interior, all
body components, and engine/transmission - COMPLETED
11/15/2008
Restore - Restoration and/or
procurement of all components to original condition (or as near
as possible). This phase includes:
Rebuild - Putting the car back together
again. This include final paint work, all seals replaced,
and final interior work.